Estate Homes v Waitakere CC - The Final Chapter?
The recently released Environment Court decision, Estate Homes
v Waitakere CC highlights the vexed issue of how far a Council
may go in looking to recover the costs of building public infrastructure
from a developer. This decision is on appeal to the High Court, but
is none the less of interest to both councils and developers.
The decision, heard on referral back from the Supreme Court, is the
latest court case in a long running dispute between a local developer,
(Estate) and the Council. The parties have been at loggerheads
over the Council's requirement that Estate pay the lion's share of
the costs associated with building an arterial road through the middle
of its Ranui subdivision, despite undisputed evidence that the subdivision
didn't generate any demand for the road, and obtained little or no
tangible benefit from it.
In essence, the Council's case was that:
(a) Estate had known about the designation for the road when it had purchased the property, and knew that the Council would require the subdivision to be built around the road (and for the road to be constructed and vested with the Council) when it applied for subdivision.
(b) The Council's policy of "connectivity", that is, ensuring that new development "fits in" with the wider network, dictated that a road of at least a collector road standard would be needed. It therefore offered to refund the difference in cost between a collector road and the arterial that was built. In its application for resource consent, Estate had indicated that it was prepared to meet the costs of a local road.
Estate's case, argued successfully before the Environment Court, was that it should not have to contribute anything towards the road, as there was no "causal nexus" between the demands generated by the subdivision and the need for the road. The subdivision was well served by other roads, and obtained little or no tangible benefit from the new arterial. The Environment Court, following the guidance offered by the 1997 decision of the Environment Court in Bletchley v Palmerston North DC, concluded that, in the absence of any such causal nexus, there was no jurisdiction to require Estate to make any contribution towards the road.
On appeal all the way through to the Supreme Court, three key factors were determined:
(a) The presence or otherwise of a "causal nexus" was not a matter that went to jurisdiction, or legal validity of the condition in terms of the established Newbury tests. However, causal nexus would undoubtedly be a matter of significance in terms of the Environment Court's role of determining the "substantive merits" of the condition requiring the road to be constructed and vested.
(b) The matter should be returned to the Environment Court to determine how much the Council ought to contribute towards the costs of the road, in order to make its requirement "fair and reasonable".
(c) In making that determination, the Environment Court could not go further than what Estate had originally suggested was its due in its consent application, that is, the difference in costs between a local road and the arterial road built.
On referral back, the Environment Court found in Estate's favour, requiring, in effect, the Council to pay Estate the difference in costs between the arterial road and a local road. In doing so, it acknowledged that connectivity policies gave the power to the Council to direct the form of the subdivision, and require the road to be built. They did not however empower the Council to effectively require Estate to pay for it.
This case follows a pattern of recent Environment Court decisions that provide guidance on how far councils can go in setting financial contributions and works requirements in consents. Such requirements must be proportionate to the needs of the subject development, and the demands it generates. This in turn requires case by case analysis by councils. Mere reference to either district plan rules or to non-statutory documents such as engineering quality standards will not be determinative of the issue.
For more information, please contact:
Melinda Dickey
Partner
t: +64 9 979 2210
e: Melinda Dickey
Andrew Green
Partner
t: +64 9 979 2172
e: Andrew Green
Linda O'Reilly
Partner
t: +64 9 979 2167
e: Linda O'Reilly
Last updated:
This article is intended to be brief in nature and should be used for information only. It should not be relied on as legal advice. |